GROUNDWATER POLLUTION CONTROL
PROGRAM
GUIDELINE #6
Minimum Design Requirements and
Common Accepted Engineering Practices:
Air Sparging Systems
Wyoming Department of Environmental Quality
Water Quality Division
(June 1998)
TABLE OF CONTENTS
INTRODUCTION
REGULATORY REQUIREMENTS
IN-WELL AERATION PROCESS DESCRIPTION
IN SITU AIR SPARGING (IAS) PROCESS DESCRIPTION
DATA NEEDS
PILOT SCALE TESTING FOR IN SITU AIR SPARGING
FULL SCALE IAS DESIGN
DESIGN REPORT FOR COMBINED IAS/SVE SYSTEM
OPERATION AND MONITORING
REFERENCES APPENDIX A APPENDIX B MINIMUM DESIGN REQUIREMENTS AND COMMON INTRODUCTION Traditionally, soil and groundwater contamination has been remedied by excavating the contaminated soil and pumping
and treating the groundwater. Soil excavation is frequently impractical and cost prohibitive to implement as the primary
corrective action. On the other hand, pump and treat technologies, while effective at containing contaminant migration,
can be extremely slow in achieving remediation due to the physical and chemical limitations inherent in the process.
Therefore, significant quantities of contaminated soils can potentially remain in the vadose (unsaturated) zone and beneath
the water table. These soils may act as a lingering source of contamination to groundwater. Air sparging is an innovative technology developed to address contamination present below the water table. Air sparging
can be divided into two distinct technologies, in well aeration and in situ air sparging (IAS). In-well aeration is the
process of injecting air into a well, producing groundwater circulation which strips the volatile fraction of contamination
present. In-situ air sparging (IAS) involves injecting air directly into water saturated soils in order to remove
contaminants through a combination of volatilization and aerobic biodegradation. Typically, IAS is used in conjunction
with soil vapor extraction (SVE) to eliminate the off-site migration of vapors while simultaneously treating unsaturated
zone soils. This document is intended to assist property owners, industry, businesses and consultants by outlining requirements for
approval of a WQD Permit to Construct. Brief overviews of both in-well aeration and IAS are included along with
common and accepted engineering practices with respect to IAS systems presented in the form of recommendations.
Recommendations are not given for in-well aeration since it has not been widely implemented and is not considered a full-scale technology. This document is intended to be used in conjunction with Guideline #2, "Applying for a Permit to
Construct for a Corrective Action System," and Guideline #5, "Soil Vapor Extraction and Bioventing Systems." Due to
the possible complex nature and variable characteristics of sites amenable to air sparging systems, information presented
herein should not be viewed as a design manual or issuance of formal policy, but merely as a general reference guide for
all parties involved. However, the design report and operation and monitoring recommendations are generally considered
to be the minimum content required by the Groundwater Pollution Control (GPC) program to evaluate an application for a
Permit to Construct. The application should include rationale describing how the remediation design meets the common
and accepted engineering practices described within this guideline. If the design deviates from these practices, the
application materials must contain justifications for the deviations. The justifications should include the information
outlined in the WQD Rules and Regulations Chapter XI, Section 5, as described in Guideline #2, "Applying for a Permit
to Construct for a Corrective Action System." REGULATORY REQUIREMENTS The approval of a 'Permit to Construct' application is required of all corrective action systems intended for sites regulated
under the Groundwater Pollution Control (GPC) program. A subsurface investigation (SSI) is required prior to the
selection and design of a corrective action system. A SSI Work plan must be submitted to the GPC program prior to
conducting field investigation work. For a detailed explanation of the application and review process, including
information to be collected during the SSI phase, the reader is referred to Guideline #2. It is highly recommended that this
document be reviewed prior to the information presented below. Guideline #5, "Soil Vapor Extraction and Bioventing
Systems," should also be reviewed since installation of an SVE system will likely be required when IAS is used. Although not covered specifically in this guidance, IAS systems may require the installation of off-gas treatment. The Air
Quality Division may require a permit for all air emissions associated with IAS/SVE systems. For more information,
contact the Air Quality Division at (307) 777-7391. Disposal or treatment of contaminated soils in conjunction with the
construction, installation or modification of an IAS system must meet the Solid and Hazardous Waste Division
requirements. For more information, contact the Solid and Hazardous Waste office at (307) 777-7752. If subsurface
injection of water generated during the construction, installation, modification or operation of an IAS system is planned, a
separate Underground Injection Control (UIC) Permit is required. For more information, contact the UIC Program at
(307) 777-7095. Whenever a discharge to surface water is proposed, the applicant must obtain a National Pollution
Discharge Elimination System (NPDES) Permit. Contact the NPDES Program Manager at (307) 777-7082 for more
information. IN-WELL AERATION PROCESS DESCRIPTION In-well aeration involves injecting air into the bottom of a well or trench screened in the saturated zone. As the injected
air travels upward through the water column, bubbles form which remove volatile and semi-volatile organic compounds
present. The upward movement of air also produces an airlift pump effect, as groundwater is pulled into the well from
deeper screened portions and out of the well from shallower screened portions. Contaminant concentrations are reduced
as groundwater circulates through the well, eliminating the need for pumping and treating the water at the surface. Although in-well aeration may sometimes prove to be more efficient than conventional pump and treat, many of the same
limitations apply to both processes. The low solubility of many contaminants and the inhibitory effect of slow mass
transfer within heterogeneous geological conditions may retard the remediation process. IN SITU AIR SPARGING (IAS) PROCESS DESCRIPTION In situ air sparging (IAS) is the process of injecting air directly into contaminated areas of the saturated zone. IAS
technology is commonly used in conjunction with soil vapor extraction (SVE) systems, allowing for treatment of vadose
zone soils, saturated zone soils and groundwater in the saturated zone. Implementing an IAS system without SVE can
potentially create a net positive pressure in the subsurface, inducing contaminant migration into previously
uncontaminated areas. In some cases it may be argued that vapor recovery systems are not necessary (i.e., in remote
locations where total potential emission rates are below acceptable levels, etc.). The discussion presented below is limited
to the IAS portion only; the reader is referred to Guideline #5, "Soil Vapor Extraction and Bioventing Systems," for
information regarding SVE recommendations and requirements. The three primary mechanisms responsible for contaminant removal during the operation of IAS systems are believed to
be: 1) in situ stripping of dissolved volatile organic compounds (VOC's), 2) volatilization of dissolved and adsorbed
contaminants found beneath the water table and in the capillary fringe, and 3) aerobic biodegradation of both dissolved
and adsorbed contamination as a consequence of additional oxygen supplied by the injected air. When an IAS system is
optimized for stimulating biodegradation it is sometimes referred to as biosparging. Typically biosparging systems are
initially operated for volatilization and stripping; the system is then fine-tuned for biodegradation. Detailed
recommendations for biosparging are beyond the scope of this guidance since the process depends greatly on site specific
characteristics. Although, general monitoring recommendation to measure biodegradation potential and performance are
provided. A typical IAS system has one or more subsurface air injection points or designated wells screened only below the water
table (see Figure 1 in Appendix A). The injected air then travels vertically and horizontally through the soil and is greatly
influenced by the degree of heterogeneity. Significant channeling can result from relatively small or subtle permeability
changes. Channeling which leads to an increase in the secondary permeability of the soil potentially reduces the
effectiveness of the IAS system due to mass transfer (e.g. diffusion) limitations. Therefore, IAS is applicable primarily at
sites where homogeneous subsurface conditions prevail. Under these conditions, IAS technology has proven to be
effective for removal of volatile organic compounds, semi volatile organic compounds and aerobically biodegradable
compounds including petroleum hydrocarbons and some chlorinated solvents. Variations of combined IAS/SVE systems
include the use of horizontal wells or trenches instead of traditional vertical well systems. The use of a line of vertical
sparge wells can be effective for intercepting a migrating plume. The mass transfer phenomenon which occur during IAS are a consequence of complex interactions between chemical,
physical and microbial processes. Currently many of these interactions are not well understood. It is also difficult to
predict the flow path taken by the air between the injection point and vadose zone soils. For these reasons, design of IAS
systems is somewhat dependent on empirical knowledge. IAS is considered to be a rapidly evolving technology with need
for continuous refinement. DATA NEEDS Since many of the driving mechanisms behind IAS systems are not fully understood, the importance of the subsurface
investigation phase cannot be overemphasized. The specific data that should be collected and evaluated in order to assess
the feasibility of in situ air sparging can be found in Guideline #2. Site specific criteria, contaminant characterization,
soil related criteria, and groundwater related criteria are outlined as requirements of the subsurface investigation (SSI)
phase. In particular, the horizontal and vertical permeability of the saturated zone and the vapor/dissolved phase
partitioning of the contaminants must be evaluated to determine the possible effectiveness of an IAS system. Dissolved
iron concentrations must also be measured when determining groundwater characteristics during the SSI phase. Iron may
precipitate during the sparging operation and could cause aquifer clogging, potentially reducing porosity and permeability.
If the following conditions are detected during the SSI phase, in situ air sparging will not be approved as a remedial
technology: It is also important to re-emphasize that the presence of fine grained materials or other geologic
heterogeneities which may limit the migration of air to the water table surface, will adversely effect the
efficiency of an air sparging system and may even promote dissolved and vapor phase contaminant migration.
Semi-confined aquifer conditions or overlying low permeability zones will require the need for an adequate
number of soil vapor extraction wells to relieve the positive pressures caused by the IAS system. If
heterogeneous conditions prevail, the applicant must obtain significant data during the SSI phase in order to
substantiate the appropriateness of air sparging as the remedial alternative and to have an effective remedial
design. PILOT SCALE TESTING FOR IN SITU AIR SPARGING In order to implement an efficient IAS system, it is necessary to understand the pattern of air flow that will
occur in the subsurface. This is generally accomplished by conducting short term pilot studies, consisting of
three sequential tests over a period of at least 24 hours. For sites with significant subsurface heterogeneities,
prolonged testing may be warranted. Typically, SVE systems must be installed in conjunction with air sparging
systems to enhance VOC removal, treat unsaturated zone soils, and/or prevent off-site migration. Approval
from the WQD must be obtained prior to proposing an IAS system without an SVE system. These tests are
required of all proposed in situ air sparging systems and should be executed in the following order: 1) Air permeability test for SVE portion of system: must be implemented, when required, as described in
Guideline #5, "Soil Vapor Extraction and Bioventing Systems," See the referenced document for test
recommendations and requirements. 2) Air sparging test with SVE turned off: this portion must be conducted for a period of at least 4 hours. 3) Combined sparge/vent test with SVE and IAS operating concurrently: final portion with both SVE and IAS
activated for no less than 12 hours. Effective implementation of these tests should: Guidelines regarding standard practices for the design and implementation of IAS testing and combined
IAS/SVE testing are presented below. Adherence to these guidelines should improve the overall quality of test
data obtained. However, it is important to note that deviations may be necessary due to widely varying site
conditions. Construction Recommendations for Pilot Test Components: Air Injection Wells: Existing groundwater monitoring wells are typically not used as air injection wells since
injection wells must be screened exclusively in the saturated zone. The following standards apply (also refer to
GPC Guideline, "Minimum Content Requirements: Sub-Surface Investigation (SSI) Work plans," for additional
minimum standards and conditions for monitoring wells): The top of the screened interval must be placed significantly below the seasonally low water table to
ensure that screen will not be exposed under any circumstance. Monitoring Components: It is apparent that current monitoring practices are inadequate in terms of
establishing a quantitative evaluation of the IAS process. Recent research has indicated that current monitoring
practices overestimate the extent of saturated zone air flow by a factor of at least 2 to 8 when compared with
results of cross borehole electrical resistance tomography. Other innovative monitoring technologies still in the
development phase include neutron probe logging and capacitance probe logging. Until these techniques are
adopted as common practice for IAS monitoring, conventional monitoring will be considered adequate for
establishing the IAS zone of influence. Therefore, an adequate number of monitoring points should be installed
in the vadose and saturated zones in order to estimate the zone of influence of the SVE and IAS systems. Miscellaneous Pilot Testing Components: SVE Portion of Pilot Test: Standard procedures and monitoring requirements of the SVE portion of the pilot test can be found in
Guideline #5, "Soil Vapor Extraction and Bioventing Systems." This portion of the test can be terminated only
after the vacuum response conditions reach equilibrium. IAS Portion of Pilot Test: Standard Procedures: Monitoring Requirements: Combined IAS/SVE Portion of Pilot Test: Standard Procedures: Monitoring Requirements: Reporting Pilot Scale Test Results: Locations of air extraction well(s) and vacuum measuring points. Locations of air injection points and
groundwater monitoring wells. Paved areas, buildings, and structures that may act as surface seals or
infiltration barriers. Buried utility trenches or other subsurface structures that may act as zones of increased
permeability. For SVE portion: For IAS portion: For combined SVE/IAS portion: FULL SCALE IAS DESIGN Pilot scale test results are usually submitted with the detailed full-scale system design. The field data obtained
from the pilot scale tests should be carefully evaluated to determine the following: 1) The intrinsic permeability of the site (both air and hydraulic permeability), including the relationship between
horizontal and vertical permeability in the vadose and saturated zone. 2) The number and location of extraction (vent) wells and injection points needed to:
Design considerations and recommendations, along with system installation and operation suggestions, are
presented below. The discussion is limited to the IAS portion of system design only. The reader is referred to
Guideline #5, "Soil Vapor Extraction and Bioventing Systems." It is also important to note that all of the
information previously presented regarding the implementation of a pilot scale test is also relevant to full scale
systems. General Design Considerations/Recommendations: When evaluating the pilot scale results the following should be taken into consideration: System Configuration and Components: Injection Well Placement and Construction: Manifold Piping: Blower: IAS Instrumentation/Flow Measuring Equipment: Other IAS System Features: DESIGN REPORT FOR COMBINED IAS/SVE SYSTEM General Requirements: Plan View: Scaled site map(s) illustrating and identifying: Process and Instrumentation Schematic: Profile Views and Cross Sections: Specifications: OPERATION AND MONITORING Operation and Maintenance Manual: The efficiency and reliability of air sparging is largely dependant on system design; however, adequate
maintenance becomes the critical factor once a system is operational. For this reason an Operation and
Maintenance (O&M) Manual must be submitted for review. A general outline representing the minimum
information required in an O&M manual can be found in Appendix C of GPC Guideline #2. In addition to the
outline, the O&M manual shall contain the following: 1) A description of systems' capabilities to operate during routine or emergency maintenance, power outages,
or other unforeseen circumstance is required. The discussion must specify details such as availability of the
owner or operator during the emergency situation, among others. 2) An analysis of length of time the remediation system can safely be off-line during emergency or maintenance
situations is also required. Factors such as potential receptors, groundwater velocity, type and amount of
contamination should be included in the discussion. Measures must be implemented to ensure that the system
will not be out of operation longer than safely feasible. Examples of such measures include parallel or
redundant equipment, adequate availability of equipment parts, operator response time and availability, etc. As-Builts: The 'as-built' construction information is due along with the first monitoring report (see performance
monitoring below) approximately 60 days after system startup. The 'as-built' submittal should include the
following: Performance Monitoring Plan: A Performance Monitoring Plan (PMP) must be submitted prior to issuance of the Permit to Construct.
Following WQD's approval of the PMP, it should be included in the O&M manual. The PMP
should include at a minimum: IAS/SVE System Monitoring Recommendations: Note: These recommendations are general guidelines only and significant variations may be warranted or
required depending on site specific characteristics. Vacuum, Pressure and Air Flow Monitoring Recommendations: Note: Air flow rates should be measured directly with a dedicated device, not estimated from blower
performance curves. Contaminant Concentration Monitoring Recommendations: Monitoring for Biosparging Performance: REFERENCES Ahfield, D.P., A. Dahmani and W. Ji, 1994. " A Conceptual Model of Field Behavior of Air Sparging and Its
Implications for Application." Groundwater Monitoring and Remediation, Fall. Boulding, J.R., 1995. Practical Handbook of Soil, Vadose Zone, and Ground-Water Contamination:
Assessment, Prevention and Remediation. CRC Press, Inc., Boca Raton, Florida. Cookson, J.T., 1995. Bioremediation Engineering: Design and Application. McGraw-Hill, Inc., New York,
New York. Fetter, C.W., 1993. Contaminant Hydrogeology. Macmillan Publishing Company, New York, New York. Freeze, R.A. and J.A. Cherry, 1979. Groundwater. Prentice-Hall, Inc., Englewood Cliffs, New Jersey. Hinchee, R.E., editor, 1994. Air Sparging for Site Remediation. Lewis Publishers, Ann Arbor, Michigan. Johnson, R.L. et. al., 1993. "An Overview of In Situ Air Sparging." Ground Water Monitoring Review. Vol.
13, No. 4, Fall. Marley, M.C. and C.J. Bruell, 1995. In Situ Air Sparging: Evaluation of Petroleum Industry Sites and
Considerations for Applicability, Design and Operation. American Petroleum Institute Publication 4609. Marley, M.C., D.J. Hazebrouck and M.T. Walsh, 1992. "The Application of In Situ Air Sparging as an
Innovative Soils and Groundwater Remediation Technology." Ground Water Monitoring Review. Vol. 12,
No. 2, Spring. Marley, M.C. et. al., 1994. "The Design of an In Situ Sparging Trench." The Proceedings of the 1994
Petroleum Hydrocarbons and Organic Chemicals in Groundwater: Prevention, Detection and Remediation
Conference, November 2-4, 1994, Houston, Texas. National Groundwater Association. U.S. EPA, 1992. "A Technology Assessment of Soil Vapor Extraction and Air Sparging." EPA/600/R-92/173. U.S. EPA, 1994. "How to Evaluate Alternative Cleanup Technologies for Underground Storage Tank Sites: A
Guide for Corrective Action Plan Reviewers." EPA/510/B-94/003. Wi, J., et. al., 1993. "Laboratory Study of Air Sparging: Air Flow Visualization." Groundwater Monitoring
and Remediation, Fall. APPENDIX A APPENDIX B GPC GUIDELINE #6 - Checklist #1: Air Sparging Pilot Tests and Detailed Evaluation of Air Sparging
Applicability This checklist is intended to aid in reviewing proposals for conducting detailed pilot tests of air sparging systems. The list also
incorporates criteria to be reviewed after performing the pilot test in order to further evaluate the potential effectiveness of using
air sparging at a site. If the answer to several questions is no, modifications to the proposed testing procedures may be warranted
or additional information should be requested.
ACCEPTED ENGINEERING PRACTICES:
AIR SPARGING SYSTEMS
Note: Product thicknesses may be difficult to contour in very low permeability (fine grained) or fractured
consolidated subsurface conditions. Please indicate product thickness at monitoring well locations.
| I. | SVE Air Permeability Test: | NA | Yes | No | Comments | ||||
| A. | Air extraction well | __ | __ | __ | _______ | ||||
| 1. | Is the proposed test well located near a highly contaminated zone, or 'hot spot'? | __ | __ | __ | _______ | ||||
| 2. | Is the proposed test well placed in the vicinity of sub-surface structures(i.e., sewer, utility lines) and/or zones that may act as preferential air flow pathways? | __ | __ | __ | _______ | ||||
| 3. | Does well construction ensure that short circuiting of air flow will not occur? | __ | __ | __ | _______ | ||||
| 4. | Is the top of the screened interval placed above the water table to avoid submergence during testing? | __ | __ | __ | _______ | ||||
| a. | Is the expected rise of the water table during testing taken into account? | __ | __ | __ | _______ | ||||
| 5. | Is the bottom of the screened interval placed at least 10 feet below the seasonal low water table? | __ | __ | __ | _______ | ||||
| 6. | If the well screen elevation criteria is not met, is groundwater pumping proposed or considered? | __ | __ | __ | _______ | ||||
| B. | Vacuum monitoring wells and probes | __ | __ | __ | _______ | ||||
| 1. | Are a minimum of three vacuum monitoring points proposed? | __ | __ | __ | _______ | ||||
| a. | Is one close to the air extraction well? | __ | __ | __ | _______ | ||||
| b. | Is one near the expected zone of influence? | __ | __ | __ | _______ | ||||
| c. | Is one within the expected zone of influence? | __ | __ | __ | _______ | ||||
| 2. | For sites with relatively homogeneous sub-surface conditions, is vacuum to be measured at or close to the same depth as the unsaturated screened interval of the extraction well? | __ | __ | __ | _______ | ||||
| 3. | For sites with relatively heterogeneous sub-surface conditions or if three dimensional computer modeling is planned, is vacuum to be measured at various depths? | __ | __ | __ | _______ | ||||
| 4. | Are the grout seals and surface caps of the proposed monitoring wells in good condition? | __ | __ | __ | _______ | ||||
| a. | Will small vacuum pressures be detected? | __ | __ | __ | _______ | ||||
| C. | Test procedures | __ | __ | __ | _______ | ||||
| 1. | Is the proposed test to be performed until equilibrium conditions are satisfied? | __ | __ | __ | _______ | ||||
| 2. | Are sufficient vacuum pressure steps (at least three) to be applied? | __ | __ | __ | _______ | ||||
| 3. | Will extraction well vacuum be held constant until vacuum measurements in monitoring points have stabilized? | __ | __ | __ | _______ | ||||
| D. | Test monitoring requirements: | __ | __ | __ | _______ | ||||
| 1. | Will the first sample of extracted VOC vapors be collected after initial purging? | __ | __ | __ | _______ | ||||
| 2. | Will barometric pressure be monitored at the beginning and end of each vacuum step? | __ | __ | __ | _______ | ||||
| 3. | Will vacuum monitoring readings be taken at nominal 15 minute intervals through each vacuum step? | __ | __ | __ | _______ | ||||
| 4. | Will the following parameters be monitored at the extraction wellhead? | __ | __ | __ | _______ | ||||
| a. | Background VOC headspace readings prior to test | __ | __ | __ | _______ | ||||
| b. | Flow rate of extraction (upstream of dilution valve) | __ | __ | __ | _______ | ||||
| c. | VOC of extracted vapors (upstream of dilution valve) | __ | __ | __ | _______ | ||||
| d. | Temperature of extracted air | __ | __ | __ | _______ | ||||
| E. | Miscellaneous components/considerations for testing | __ | __ | __ | _______ | ||||
| 1. | Does blower/vacuum pump have explosion proof: | __ | __ | __ | _______ | ||||
| a. | motor | __ | __ | __ | _______ | ||||
| b. | starter | __ | __ | __ | _______ | ||||
| c. | electrical system | __ | __ | __ | _______ | ||||
| 2. | Is a water trap/particulate filter needed? | __ | __ | __ | _______ | ||||
| 3. | Is the need for off-gas treatment during tested addressed or evaluated? | __ | __ | __ | _______ | ||||
| II. | Air Sparging Test (with SVE off): | NA | Yes | No | Comments | ||||
| A. | Air injection well(s)/point(s) | __ | __ | __ | _______ | ||||
| 1. | Is the proposed test well/point located in an area of significant groundwater contamination, or 'hot spot'? | __ | __ | __ | _______ | ||||
| 2. | Is the proposed test well placed in the vicinity of sub-surface structures (i.e., sewer lines, utility lines) and/or zones that may act as preferential air flow pathways? | __ | __ | __ | _______ | ||||
| 3. | Is the top of the screened interval placed significantly below the seasonally low water table to ensure that the screen will not be exposed under any circumstance? | __ | __ | __ | _______ | ||||
| 4. | Is the top of the screened interval placed sufficiently below the contaminated area to be remediated? | __ | __ | __ | _______ | ||||
| a. | Is the top of the screened interval 5 - 15 feet below the deepest contamination under low water table conditions? | __ | __ | __ | _______ | ||||
| (1) | Is the depth of the top of the screened interval less than 30 - 40 feet below the ground surface? | __ | __ | __ | _______ | ||||
| (2) | Is the depth of the top of the screened interval less than 20 feet below the water table? | __ | __ | __ | _______ | ||||
| 5. | Is the screen length between 2 - 5 feet? | __ | __ | __ | _______ | ||||
| 6. | Does well construction ensure that short circuiting of air flow will not occur? | __ | __ | __ | _______ | ||||
| B. | Monitoring components | __ | __ | __ | _______ | ||||
| 1. | Saturated zone monitoring wells: | __ | __ | __ | _______ | ||||
| a. | Are sufficient monitoring wells/points proposed to adequately perform test? | __ | __ | __ | _______ | ||||
| b. | Are the monitoring wells constructed properly? | __ | __ | __ | _______ | ||||
| 2. | Unsaturated zone vacuum monitoring wells: | __ | __ | __ | _______ | ||||
| a. | Are a minimum of three vacuum monitoring points proposed? | __ | __ | __ | _______ | ||||
| (1) | Is one close to the air injection well? | __ | __ | __ | _______ | ||||
| (2) | Is one near the expected zone of influence? | __ | __ | __ | _______ | ||||
| (3) | Is one within the expected zone of influence? | __ | __ | __ | _______ | ||||
| b. | Are the grout seals and surface caps of the proposed monitoring wells in good condition? | __ | __ | __ | _______ | ||||
| (1) | Will small vacuum pressures be detected? | __ | __ | __ | _______ | ||||
| C. | Miscellaneous components | __ | __ | __ | _______ | ||||
| 1. | Is an oil free compressor going to be used? | __ | __ | __ | _______ | ||||
| 2. | If a standard compressor is proposed, will it be equipped with downstream coalescing and particulate filters? | __ | __ | __ | _______ | ||||
| 3. | Are check valves going to be used between the injection well and compressor? | __ | __ | __ | _______ | ||||
| 4. | Is a heat exchanger proposed or needed? | __ | __ | __ | _______ | ||||
| D. | Test procedures | __ | __ | __ | _______ | ||||
| 1. | Are at least 2 different injection pressures proposed? | __ | __ | __ | _______ | ||||
| a. | Will pressure be held constant for a minimum of two hours at each step? | __ | __ | __ | _______ | ||||
| b. | Are the injection pressures in the range of 2 - 60 psig? | __ | __ | __ | _______ | ||||
| (1) | Will the pressure be sufficient to overcome hydraulic head and capillary forces? | __ | __ | __ | _______ | ||||
| (2) | Is the injection pressure less than 3 times the static hydraulic pressure calculated at the top of the screen? | __ | __ | __ | _______ | ||||
| (3) | Is the injection pressure less than 80% of the total pressure exerted by the weight of the soil and water above the top of the screen? | __ | __ | __ | _______ | ||||
| 2. | Is the expected air flow rate in the range of 2 scfm to 25 scfm? | __ | __ | __ | _______ | ||||
| 3. | Is a tracer gas going to be used? | __ | __ | __ | _______ | ||||
| a. | Is helium going to be used? | __ | __ | __ | _______ | ||||
| E. | Test monitoring requirements | __ | __ | __ | _______ | ||||
| 1. | Will pressure readings (in vadose zone) and flow rate readings (at the injection point) be taken several times at each valve setting? | __ | __ | __ | _______ | ||||
| 2. | Will groundwater mounding be measured periodically at the injection point and in multiple monitoring wells? | __ | __ | __ | _______ | ||||
| 3. | Will subsurface gas phase contaminant (VOC's) concentration changes in vadose zone wells/probes and water table wells be measured? | __ | __ | __ | _______ | ||||
| 4. | Will changes in dissolved oxygen (DO) in groundwater monitoring wells be monitored? | __ | __ | __ | _______ | ||||
| 5. | Will concentration of tracer gas (when used) be measured in the vadose zone? | __ | __ | __ | _______ | ||||
| III. | Combined SVE/Air Sparging Test | NA | Yes | No | Comments | ||||
| A. | Test procedures | __ | __ | __ | _______ | ||||
| 1. | Will the SVE extraction well and the sparging injection well be operated concurrently over a period of at least 12 hours? | __ | __ | __ | _______ | ||||
| 2. | Will the SVE extraction rate exceed the air sparge injection rate? | __ | __ | __ | _______ | ||||
| a. | Is the proposed air sparging rate between 205 to 80% of the SVE extraction rate? | __ | __ | __ | _______ | ||||
| B. | Test monitoring requirements | __ | __ | __ | _______ | ||||
| 1. | Will SVE vacuum and flow rates and sparging pressure and flowrates be measured periodically? | __ | __ | __ | _______ | ||||
| 2. | Will pressure in the vadose zone be monitored? | __ | __ | __ | _______ | ||||
| 3. | Will groundwater mounding be measured periodically at the injection point and in multiple monitoring wells? | __ | __ | __ | _______ | ||||
| 4. | Will subsurface gas phase contaminant (VOC's) concentration changes be measured in vadose zone wells/probes and water table wells? | __ | __ | __ | _______ | ||||
| 5. | Will changes in dissolved oxygen (DO) in groundwater monitoring wells be monitored? | __ | __ | __ | _______ | ||||
| 6. | If biodegradation potential is to be evaluated for future system optimization, will CO2 gas be measured in vadose zone wells and dissolved in groundwater? | __ | __ | __ | _______ | ||||
| IV. | Reporting results for all tests: | NA | Yes | No | Comments | ||||
| A. | A site map drawn to scale indicating: | __ | __ | __ | _______ | ||||
| 1. | Locations of: | ||||||||
| a. | air extraction well(s) | __ | __ | __ | _______ | ||||
| b. | air injection well(s) | __ | __ | __ | _______ | ||||
| c. | vacuum measuring points | __ | __ | __ | _______ | ||||
| d. | groundwater monitoring wells | __ | __ | __ | _______ | ||||
| 2. | Paved areas, buildings, and other surface structures | __ | __ | __ | _______ | ||||
| 3. | Buried utility trenches or other subsurface structures | __ | __ | __ | _______ | ||||
| B. | Descriptions of field equipment and procedures used during testing | __ | __ | __ | _______ | ||||
| C. | For SVE portion: | __ | __ | __ | _______ | ||||
| 1. | Table showing: | __ | __ | __ | _______ | ||||
| a. | Operating flow rates at different vacuum steps | __ | __ | __ | _______ | ||||
| b. | Vacuum measured at monitoring points | __ | __ | __ | _______ | ||||
| c. | Duration of each vacuum step applied | __ | __ | __ | _______ | ||||
| d. | Barometric pressure readings | __ | __ | __ | _______ | ||||
| Note: times readings/measurements taken should be included | __ | __ | __ | _______ | |||||
| 2. | Plot of soil vapor vacuum vs. horizontal distance from the extraction well | __ | __ | __ | _______ | ||||
| a. | Semi-log paper with vacuum on log scale (y-axis) | __ | __ | __ | _______ | ||||
| b. | Linear regression analysis performed | __ | __ | __ | _______ | ||||
| 3. | Table showing: | __ | __ | __ | _______ | ||||
| a. | VOC levels in extracted vapors | __ | __ | __ | _______ | ||||
| b. | Temperature of extracted vapor | __ | __ | __ | _______ | ||||
| Note: times readings/measurements taken should be included | __ | __ | __ | _______ | |||||
| 4. | Average VOC mass removal rates calculated from extraction concentrations and flow rates for each vacuum step | __ | __ | __ | _______ | ||||
| 5. | Sampling methods and procedures | __ | __ | __ | _______ | ||||
| 6. | Boring logs and 'as-built' construction diagrams for: | __ | __ | __ | _______ | ||||
| a. | air extraction well(s) | __ | __ | __ | _______ | ||||
| b. | vacuum monitoring wells/points | __ | __ | __ | _______ | ||||
| D. | For air sparging portion | __ | __ | __ | _______ | ||||
| 1. | Table showing: | __ | __ | __ | _______ | ||||
| a. | Operating flow rates at different injection pressures | __ | __ | __ | _______ | ||||
| b. | Duration of each injection step, including time readings taken | __ | __ | __ | _______ | ||||
| 2. | Table showing: | __ | __ | __ | _______ | ||||
| a. | Monitoring well/vapor probe VOC measurements taken with FID/PID | __ | __ | __ | _______ | ||||
| b. | Time of reading/measurement | __ | __ | __ | _______ | ||||
| 3. | Table of water level measurements, including time measurement taken | __ | __ | __ | _______ | ||||
| 4. | Table of DO readings at monitoring wells (with time of reading noted) | __ | __ | __ | _______ | ||||
| 5. | Plot of soil pressure in vadose zone vs. distance from sparge well | __ | __ | __ | _______ | ||||
| 6. | Plot of soil gas measurements (VOC's and O2, CO2 and He when measured) vs. time | __ | __ | __ | _______ | ||||
|
|
E. | For combined SVE/air sparging portion | __ | __ | __ | _______ | |||
| 1. | Table showing: | __ | __ | __ | _______ | ||||
| a. | operating flow rates | __ | __ | __ | _______ | ||||
| b. | vacuums | __ | __ | __ | _______ | ||||
| c. | pressures | __ | __ | __ | _______ | ||||
| d. | time measurements taken | __ | __ | __ | _______ | ||||
| 2. | Table showing: | __ | __ | __ | _______ | ||||
| a. | VOC levels in extracted vapors (measured prior to any off-gas treatment system) | __ | __ | __ | _______ | ||||
| b. | temperature of extracted vapor | __ | __ | __ | _______ | ||||
| c. | time readings were taken | __ | __ | __ | _______ | ||||
| Note: extraction concentrations must be converted to average VOC removal rates for the test | __ | __ | __ | _______ | |||||
| 3. | Table of water level measurements, including time measurement taken | __ | __ | __ | _______ | ||||
| 4. | Table of DO readings at monitoring wells (with time of reading noted) | __ | __ | __ | _______ | ||||
| 5. | Plot of changes in water table elevation vs. time for different observation wells at various distances from sparge well | __ | __ | __ | _______ | ||||
| 6. | Plot of soil gas measurements vs. time | __ | __ | __ | _______ | ||||
| a. | VOC's | __ | __ | __ | _______ | ||||
| b. | O2 and CO2 (when measured) | __ | __ | __ | _______ | ||||
| 7. | Plot of DO measured in groundwater wells vs. distance from sparging well | __ | __ | __ | _______ | ||||
| V. | Additional criteria for Detailed Evaluation of Air Sparging Applicability (optional) | NA | Yes | No | Comments | ||||
| A. | Is the intrinsic permeability greater than 10-9 cm2? | __ | __ | __ | _______ | ||||
GPC GUIDELINE #6 - Checklist #2: Administrative Checklist for Air Sparging Design Report
This checklist is intended to aid in reviewing the design report and application materials for an air sparging system. The list incorporates an evaluation of the system design as well as completeness of the application package.
| I. | Evaluation of Air Sparging System Design | NA | Yes | No | Comments | ||||||
| A. | Design zone of influence: | __ | __ | __ | _______ | ||||||
| 1. | Has the zone of influence been calculated/estimated for each geologic strata or soil type in the targeted contaminated area? | __ | __ | __ | _______ | ||||||
| 2. | Does the zone of influence for the extraction wells fall in the range of 5 to 100 feet? | __ | __ | __ | _______ | ||||||
| a. | Was this value reached by averaging the radial distances measured for: | __ | __ | __ | _______ | ||||||
| (1) | positive pressure in the vadose zone | __ | __ | __ | _______ | ||||||
| (2) | DO in the saturated zone | __ | __ | __ | _______ | ||||||
| (3) | increases in vadose zone VOC concentrations during the air sparging portion of the pilot test? | __ | __ | __ | _______ | ||||||
| b. | Was this value reached by using one to two times the injection depth as an approximation? | __ | __ | __ | _______ | ||||||
| (1) | If so, are site soils relatively homogeneous in the area of concern? | __ | __ | __ | _______ | ||||||
| B. | Extraction well design: | ||||||||||
| 1. | Is the type of well proposed (horizontal or vertical) appropriate for the site conditions? | __ | __ | __ | _______ | ||||||
| 2. | Does well construction ensure that short circuiting of air flow will not occur? | __ | __ | __ | _______ | ||||||
| 3. | Is the top of the screened interval placed above the water table to avoid submergence? | __ | __ | __ | _______ | ||||||
| a. | Is the expected rise of the water table taken into account? | __ | __ | __ | _______ | ||||||
| 4. | Is the bottom of the screened interval placed at least 10 feet below the seasonal low water table? | __ | __ | __ | _______ | ||||||
| 5. | If the well screen elevation criteria is not met, is groundwater pumping proposed or considered? | __ | __ | __ | _______ | ||||||
| 6. | Is the proposed well density appropriate and adequate, given the total area to be remediated and the zone of influence for each well? | __ | __ | __ | _______ | ||||||
| 7. | Do the proposed well screen intervals match the soil conditions at the site? | __ | __ | __ | _______ | ||||||
| a. | Are the wells screened throughout the entire zone of contamination? | __ | __ | __ | _______ | ||||||
| C. | Injection well design: | __ | __ | __ | _______ | ||||||
| 1. | Is the proposed test well placed in the vicinity of sub-surface structures (i.e., sewer lines, utility lines) and/or zones that may act as preferential air flow pathways? | __ | __ | __ | _______ | ||||||
| 2. | Is the top of the screened interval placed significantly below the seasonally low water table to ensure that the screen will not be exposed under any circumstance? | __ | __ | __ | _______ | ||||||
| 3. | Is the top of the screened interval placed sufficiently below the contaminated area to be remediated? | __ | __ | __ | _______ | ||||||
| a. | Is the top of the screened interval 5 - 15 feet below the deepest contamination under low water table conditions? | __ | __ | __ | _______ | ||||||
| (1) | Is the depth of the top of the screened interval less than 30 - 40 feet below the ground surface? | __ | __ | __ | _______ | ||||||
| (2) | Is the depth of the top of the screened interval less than 20 feet below the water table? | __ | __ | __ | _______ | ||||||
| 4. | Is the screen length between 2 - 5 feet? | __ | __ | __ | _______ | ||||||
| 5. | Does well construction ensure that short circuiting of air flow will not occur? | __ | __ | __ | _______ | ||||||
| 6. | Is the number and placement of wells appropriate and adequate, given the total area to be remediated and the zone of influence of each well? | __ | __ | __ | _______ | ||||||
| 7. | Are the injection pressures in the range of 2 - 60 psig? | __ | __ | __ | _______ | ||||||
| a. | Will the pressure be sufficient to overcome hydraulic head and capillary forces? | __ | __ | __ | _______ | ||||||
| b. | Is the injection pressure less than 3 times the static hydraulic pressure calculated at the top of the screen? | __ | __ | __ | _______ | ||||||
| c. | Is the injection pressure less than 80% of the total pressure exerted by the weight of the soil and water above the top of the screen? | __ | __ | __ | _______ | ||||||
| 8. | Is the expected air flow rate in the range of 2 scfm to 25 scfm? | __ | __ | __ | _______ | ||||||
| D. | Manifold piping: | __ | __ | __ | _______ | ||||||
| 1. | Is the piping sloped toward the extraction wells? | __ | __ | __ | _______ | ||||||
| 2. | Are winterization provisions included? | __ | __ | __ | _______ | ||||||
| E. | Blower, vacuum pump or compressor: | __ | __ | __ | _______ | ||||||
| 1. | For SVE system: | __ | __ | __ | _______ | ||||||
| a. | Is the blower/vacuum pump selected appropriate for the desired vacuum conditions? | __ | __ | __ | _______ | ||||||
| b. | Does blower/vacuum pump have explosion proof: | __ | __ | __ | _______ | ||||||
| (1) | motor | __ | __ | __ | _______ | ||||||
| (2) | starter | __ | __ | __ | _______ | ||||||
| (3) | electrical system | __ | __ | __ | _______ | ||||||
| c. | Is a water trap/particulate filter needed? | __ | __ | __ | _______ | ||||||
| d. | Has approval been obtained from AQD for off-gas treatment? | __ | __ | __ | _______ | ||||||
| e. | Is the proposed system appropriate for the contaminant concentrations? | __ | __ | __ | _______ | ||||||
| 2. | For sparging system: | __ | __ | __ | _______ | ||||||
| a. | Is the air compressor selected appropriate for the desired sparge pressure? | __ | __ | __ | _______ | ||||||
| b. | Is an oil free compressor going to be used? | __ | __ | __ | _______ | ||||||
| c. | If a standard compressor is proposed, will it be equipped with downstream coalescing and particulate filters? | __ | __ | __ | _______ | ||||||
| d. | Are check valves going to be used between the injection well and compressor? | __ | __ | __ | _______ | ||||||
| e. | Is a heat exchanger proposed or needed? | __ | __ | __ | _______ | ||||||
| 3. | Is a discharge muffler needed to avoid nuisance conditions? | __ | __ | __ | _______ | ||||||
| F. | Miscellaneous/optional components: | __ | __ | __ | _______ | ||||||
| 1. | Are horizontal injection/extraction wells proposed? | __ | __ | __ | _______ | ||||||
| a. | Are they appropriate given site conditions? | __ | __ | __ | _______ | ||||||
| II. | Design Report Completeness | NA | Yes | No | Comments | ||||||
| A. | General Requirements | __ | __ | __ | _______ | ||||||
| 1. | Discussion/justification of system design with a description of the systems' capabilities for remediating: | __ | __ | __ | _______ | ||||||
| a. | soil | __ | __ | __ | _______ | ||||||
| b. | groundwater | __ | __ | __ | _______ | ||||||
| c. | smear zone | __ | __ | __ | _______ | ||||||
| 2. | Engineering calculations for determining extraction and injection well spacing including zone of influence estimates for both SVE and sparging wells | __ | __ | __ | _______ | ||||||
| a. | Assumptions clearly stated | __ | __ | __ | _______ | ||||||
| b. | References for formulas/methods used clearly stated | __ | __ | __ | _______ | ||||||
| c. | If any computer modeling is used, model assumptions and results included | __ | __ | __ | _______ | ||||||
| 3. | Discussion of free product removal, when necessary | __ | __ | __ | _______ | ||||||
| 4. | Discussion of the ratio of extracted air to injected air when SVE is required | __ | __ | __ | _______ | ||||||
| 5. | Discussion of the need for treating water that is extracted (i.e., pumped or in water trap) | __ | __ | __ | _______ | ||||||
| a. | If treatment is required, technology to be used is described | __ | __ | __ | _______ | ||||||
| b. | Meets requirements of Chapter XI, sections 6 and 7 | __ | __ | __ | _______ | ||||||
| 6. | Brief description of off-gas treatment proposed (when treatment is required by AQD) | __ | __ | __ | _______ | ||||||
| 7. | Design drawings must be scaled to show sufficient detail | __ | __ | __ | _______ | ||||||
| 8. | Winterization provisions submitted | __ | __ | __ | _______ | ||||||
| B. | Plan View(s): | __ | __ | __ | _______ | ||||||
| 1. | Scaled site map(s) illustrating and identifying: | __ | __ | __ | _______ | ||||||
| a. | contaminated area to be remediated | __ | __ | __ | _______ | ||||||
| b. | dissolved iso-concentration contours and free product thickness contours | __ | __ | __ | _______ | ||||||
| 2. | Potentiometric surface | __ | __ | __ | _______ | ||||||
| 3. | Location of proposed and existing extraction/injection wells and monitoring points/wells | __ | __ | __ | _______ | ||||||
| a. | depth of screened interval identified for all wells | __ | __ | __ | _______ | ||||||
| 4. | Zone of influence of each extraction and injection well | __ | __ | __ | _______ | ||||||
| 5. | Location of manifold, blower and other equipment | __ | __ | __ | _______ | ||||||
| 6. | Subsurface structures present (i.e., underground utilities, etc.) | __ | __ | __ | _______ | ||||||
| 7. | Paved areas, buildings and surface structures present | __ | __ | __ | _______ | ||||||
| a. | residential areas | __ | __ | __ | _______ | ||||||
| b. | basements | __ | __ | __ | _______ | ||||||
| 8. | Paved or sealed surface areas | __ | __ | __ | _______ | ||||||
| 9. | Aboveground surface seals (if proposed) | __ | __ | __ | _______ | ||||||
| C. | Process and Instrumentation Schematic: | ||||||||||
| 1. | Process flow diagram indicating: | __ | __ | __ | _______ | ||||||
| a. | all components | __ | __ | __ | _______ | ||||||
| b. | direction of air/water flow | __ | __ | __ | _______ | ||||||
|
|
D. | Profile Views and Cross Sections: | __ | __ | __ | _______ | |||||
| 1. | Typical monitoring well/point cross section construction detail | __ | __ | __ | _______ | ||||||
| a. | depths of screened interval identified on plan view for all wells | __ | __ | __ | _______ | ||||||
| 2. | Representative hydrogeologic cross sections | __ | __ | __ | _______ | ||||||
| a. | profile view of highest contamination zone illustrating and identifying | __ | __ | __ | _______ | ||||||
| (1) | elevations of ground surface | __ | __ | __ | _______ | ||||||
| (2) | boundaries between differing lithologies and/or permeabilities | __ | __ | __ | _______ | ||||||
| (3) | water table | __ | __ | __ | _______ | ||||||
| (4) | screened interval of extraction wells lying in cross section | __ | __ | __ | _______ | ||||||
| (5) | analytical soil sampling results at respective depths | __ | __ | __ | _______ | ||||||
| E. | Specifications: | __ | __ | __ | _______ | ||||||
| 1. | Size and type of blower/vacuum pump | __ | __ | __ | _______ | ||||||
| a. | range of operating flow rates | __ | __ | __ | _______ | ||||||
| b. | manufacturers performance curves | __ | __ | __ | _______ | ||||||
| c. | vacuum levels | __ | __ | __ | _______ | ||||||
| 2. | Piping specifications | __ | __ | __ | _______ | ||||||
| a. | sizing | __ | __ | __ | _______ | ||||||
| b. | compatibility of piping materials with contaminants | __ | __ | __ | _______ | ||||||
| 3. | Maximum flow ratings for | __ | __ | __ | _______ | ||||||
| a. | activated carbon units | __ | __ | __ | _______ | ||||||
| b. | oil-water separators | __ | __ | __ | _______ | ||||||
| c. | other treatment units proposed | __ | __ | __ | _______ | ||||||
| 4. | Specifications of measuring instruments | __ | __ | __ | _______ | ||||||
| a. | vacuum and flow gauges | __ | __ | __ | _______ | ||||||
|
|
F. | Operation and Monitoring: | |||||||||
| 1. | 'Operation and Maintenance Manual' additional checklist | __ | __ | __ | _______ | ||||||
| a. | Description of systems' capabilities to operate during: | ||||||||||
| (1) | routine maintenance | __ | __ | __ | _______ | ||||||
| (2) | emergency maintenance | __ | __ | __ | _______ | ||||||
| (3) | power outages | __ | __ | __ | _______ | ||||||
| (4) | other(s) | __ | __ | __ | _______ | ||||||
| b. | Analysis of length of time system can safely be off-line | __ | __ | __ | _______ | ||||||
| c. | Measures taken to ensure that system will not be off-line for unsafe amount of time | __ | __ | __ | _______ | ||||||
| (1) | parallel or redundant equipment | __ | __ | __ | _______ | ||||||
| (2) | adequate availability of system parts | __ | __ | __ | _______ | ||||||
| (3) | operator response time and availability | __ | __ | __ | _______ | ||||||
| d. | OSHA requirements included | __ | __ | __ | _______ | ||||||
| e. | Health and Safety Plan (HASP) required and included | __ | __ | __ | _______ | ||||||
| f. | Spill Prevention, Control and Countermeasures (SPCC) Plan required and included | __ | __ | __ | _______ | ||||||
| 2. | Adequate frequency of reporting monitoring events/results | __ | __ | __ | _______ | ||||||
| 3. | 'Operation and Maintenance Manual' additional checklist | __ | __ | __ | _______ | ||||||
| a. | Description of systems' capabilities to operate during: | ||||||||||
| (1) | routine maintenance | __ | __ | __ | _______ | ||||||
| (2) | emergency maintenance | __ | __ | __ | _______ | ||||||
| (3) | power outages | __ | __ | __ | _______ | ||||||
| (4) | other(s) | __ | __ | __ | _______ | ||||||
| b. | Analysis of length of time system can safely be off-line | __ | __ | __ | _______ | ||||||
| c. | Measures taken to ensure that system will not be off-line for unsafe amount of time | __ | __ | __ | _______ | ||||||
| (1) | parallel or redundant equipment | __ | __ | __ | _______ | ||||||
| (2) | adequate availability of system parts | __ | __ | __ | _______ | ||||||
| (3) | operator response time and availability | __ | __ | __ | _______ | ||||||
| d. | OSHA requirements included | __ | __ | __ | _______ | ||||||
| e. | Health and Safety Plan (HASP) required and included | __ | __ | __ | _______ | ||||||
| f. | Spill Prevention, Control and Countermeasures (SPCC) Plan required and included | __ | __ | __ | _______ | ||||||
| 4. | Performance Monitoring Plan | __ | __ | __ | _______ | ||||||
| a. | Operating vacuum and pressure monitoring frequency: | __ | __ | __ | _______ | ||||||
| (1) | daily monitoring for first week | __ | __ | __ | _______ | ||||||
| (2) | weekly monitoring for first month | __ | __ | __ | _______ | ||||||
| (3) | at least monthly after startup | __ | __ | __ | _______ | ||||||
| Note: | Measurements to be taken at each injection wellhead, extraction wellhead, manifold branch, at blower and at stack. | __ | __ | __ | _______ | ||||||
| b. | Vacuum in surrounding wells monitoring frequency: | __ | __ | __ | _______ | ||||||
| (1) | Same as air permeability test: | __ | __ | __ | _______ | ||||||
| (a) | 15 minute intervals for 1 - 2 hours | __ | __ | __ | _______ | ||||||
| (b) | weekly for first month | __ | __ | __ | _______ | ||||||
| c. | Air flow monitoring: | __ | __ | __ | _______ | ||||||
| (1) | Monitoring of total system air flow: | __ | __ | __ | _______ | ||||||
| (a) | daily monitoring for first week | __ | __ | __ | _______ | ||||||
| (b) | weekly monitoring for first month | __ | __ | __ | _______ | ||||||
| (c) | at least monthly after startup | __ | __ | __ | _______ | ||||||
| Note: | Air flow rates to measured directly with dedicated device and not estimated from blower performance curves | __ | __ | __ | _______ | ||||||
| Measurements to be taken at each injection wellhead, extraction wellhead, manifold branch, at blower and at stack | __ | __ | __ | _______ | |||||||
| (2) | Monitoring of air flow rates at each extraction well | __ | __ | __ | _______ | ||||||
| (a) | measured at startup and subsequently if changes observed | __ | __ | __ | _______ | ||||||
| d. | Groundwater level monitoring: | __ | __ | __ | _______ | ||||||
| (1) | Levels taken daily for first week | __ | __ | __ | _______ | ||||||
| (2) | On an as-needed basis thereafter | __ | __ | __ | _______ | ||||||
| e. | Flow balancing: | __ | __ | __ | _______ | ||||||
| (1) | Flow rate balanced to obtain nearly equivalent air flow rate not equivalent vacuums | __ | __ | __ | _______ | ||||||
| (2) | Flow rate to be optimized in order to maximize mass removal rates | __ | __ | __ | _______ | ||||||
| f. | VOC concentration monitoring: | __ | __ | __ | _______ | ||||||
| (1) | Monitoring of system effluent prior to off-gas treatment: | __ | __ | __ | _______ | ||||||
| (a) | Type of instrument to be used: | __ | __ | __ | _______ | ||||||
| i) | FID (preferable) | __ | __ | __ | _______ | ||||||
| ii) | PID | __ | __ | __ | _______ | ||||||
| (b) | daily monitoring for first week | __ | __ | __ | _______ | ||||||
| (c) | weekly for first month | __ | __ | __ | _______ | ||||||
| (d) | at least monthly after startup, done concurrently with air flow | __ | __ | __ | _______ | ||||||
| (2) | Off-gas VOC sampling: | __ | __ | __ | _______ | ||||||
| (a) | Description of sampling procedures | __ | __ | __ | _______ | ||||||
| (b) | Description of lab analysis to be performed | __ | __ | __ | _______ | ||||||
| i) | BTEX | __ | __ | __ | _______ | ||||||
| ii) | TPH | __ | __ | __ | _______ | ||||||
| iii) | others | __ | __ | __ | _______ | ||||||
| (c) | To be performed at system startup and at acceptable frequency following startup | __ | __ | __ | _______ | ||||||
| (d) | Air temperature measurement taken concurrently with VOC monitoring | __ | __ | __ | _______ | ||||||
| 5. | First monitoring report | __ | __ | __ | _______ | ||||||
| a. | All of monitoring results as described above | __ | __ | __ | _______ | ||||||
| b. | Deviations from plans and specs in design report | __ | __ | __ | _______ | ||||||
| c. | Complete "as-built" construction drawings and specs | __ | __ | __ | _______ | ||||||