VRP Flow Chart
| 1. Volunteer submits application to DEQ. Click here to see Eligibility and Application web page. | |||
| Contamination limited to soil? You may be eligible for a steamlined process. Click here for more information. | |||
| 2. DEQ determines site eligibility within 45 days from date of application. | |||
| 3. Volunteer initiates public notice and comment period. | |||
| 4. Site characterization completed and approved by DEQ? | |||
| No | Yes, skip to step 7 with DEQ concurrence. | ||
| 5. DEQ and Volunteer sign a preliminary remediation agreement (PRA). | |||
| 6. Volunteer completes site characterization. Click here for the Site Characterization web page. | |||
| 7a. Volunteer reports site characterization and risk assessment. | |||
| 7b. Volunteer evaluates remedies. | |||
| 8. DEQ and Volunteer negotiate a draft remedy agreement (RA). Click here for the Remedy Selection and Implementation web page. | |||
| 9. Volunteer initiates the remedy public notice. | |||
| 10a. DEQ and Volunteer sign remedy agreement. Volunteer records the remedy agreement in the appropriate county clerk's office. | |||
| 10b. Volunteer may apply for Covenant Not to Sue | |||
| 11. Volunteer implements the remedy | |||
| 12. Volunteer demonstrates and DEQ approves that cleanup objectives have been met. | |||
| 13. Volunteer applies to DEQ for Certificate of Completion or No Further Action letter. Click here for the Incentives web page. | |||